Skip to content

Making the right call before the route is set

Creyke Beck to High Marnham.

At a glance

Strengthening the transmission network

The Creyke Beck to High Marnham project is all about strengthening the transmission network across the Humberside and Lincolnshire regions. The scheme will increase boundary transfer capability, create opportunities for future generation connections, and help keep the network compliant with the Security and Quality of Supply Standard (SQSS).

icon

Building a 90km transmission line

At its heart is a new double-circuit overhead line, roughly 90km long, connecting the new Creyke Beck North and High Marnham 400kV air-insulated switchgear (AIS) substations.

icon

The right approach

But before you can build a 90km transmission line, you need to work out where it should go. This is the kind of thing that Yova does best.

The challenge

We joined the project during the pre-development consent order (DCO) phase – when early-stage optioneering can have a huge impact on everything that follows.

With a project of this scale, there are countless possible routing permutations, and a huge number of constraints to consider. Assessing those options manually would be slow, and unlikely to give the complete picture needed for confident decision-making.

The challenge was to turn all that complexity into something useful: useful data that could be properly analysed, so that we could compare options on technical feasibility, cost, and risk. And all while also considering the wider environmental and socio-economic picture.

hi-vis jacket Yova men on site

Our approach

There were some obvious options, but we knew we needed to look beyond these. So, we built the tools to explore everything properly.

hi-vis jacket Yova men on site

Smarter optioneering

We developed bespoke software combining mapping tools with custom algorithms to work through high volumes of potential line-routing permutations. That gave the feasibility and optioneering process a level of rigour that manual assessment could never match – allowing options to be assessed systematically and efficiently.

Putting a price on every option

We developed cost-loaded models to estimate and compare completion costs across the different options. After all, the cheapest route on a map isn’t necessarily the cheapest route to build.

Finding the constraints early

We gathered constraint data and identified potential hazards at an early stage, helping ensure that decisions were based on the full picture rather than what looked simplest at first glance.

Testing what can actually be built

A route can work beautifully on paper and still be a nightmare to construct. To understand the difference, we produced stage-by-stage drawings to assess the constructability of each option, and identify potential issues before they became expensive problems.

Making risk visible

We brought the analysis together in holistic risk assessment reports, helping keep expectations around outturn costs grounded in the realities of delivery.

The outcome

Our analysis and methodologies directly informed the strategic optioneering process, giving the National Grid the evidence needed to make properly-informed decisions.

By bringing together detailed feasibility studies, cost modelling, constructability analysis, and risk assessment, we helped put the trade-offs on the table. We balanced technical, economic, environmental and socio-economic considerations fairly and open-mindedly, rather than simply choosing the easiest option on paper.

This project was a great example of Yova doing what we do best: combining technical expertise, smart thinking and practical insight to tackle complex infrastructure challenges.

Because when you’re planning 90km of new transmission infrastructure, the right answer is worth finding before you start building.

Construction site

Related case studies

Yova engineers on site hi-vis jackets

Bringing clarity to complex engineering interface

Bringing clarity to complex engineering interface

Supporting SSEN’s engineering interface with National Grid on the Iver 132kV GIS programme.

Site survey yova - power grid

Making the right call before a route is set

Making the right call before a route is set

Creyke Beck to High Marnham.

Norwich Main substation extension

Powering the next phase of the energy transition

Powering the next phase of the energy transition

Norwich Main substation extension.

Stuck? You need Yova

Yova is your go-to partner when projects slow down. We’ll get you moving again.