Making the right call before the route is set
Creyke Beck to High Marnham.
The challenge
We joined the project during the pre-development consent order (DCO) phase – when early-stage optioneering can have a huge impact on everything that follows.
With a project of this scale, there are countless possible routing permutations, and a huge number of constraints to consider. Assessing those options manually would be slow, and unlikely to give the complete picture needed for confident decision-making.
The challenge was to turn all that complexity into something useful: useful data that could be properly analysed, so that we could compare options on technical feasibility, cost, and risk. And all while also considering the wider environmental and socio-economic picture.
Our approach
There were some obvious options, but we knew we needed to look beyond these. So, we built the tools to explore everything properly.
The outcome
Our analysis and methodologies directly informed the strategic optioneering process, giving the National Grid the evidence needed to make properly-informed decisions.
By bringing together detailed feasibility studies, cost modelling, constructability analysis, and risk assessment, we helped put the trade-offs on the table. We balanced technical, economic, environmental and socio-economic considerations fairly and open-mindedly, rather than simply choosing the easiest option on paper.
This project was a great example of Yova doing what we do best: combining technical expertise, smart thinking and practical insight to tackle complex infrastructure challenges.
Because when you’re planning 90km of new transmission infrastructure, the right answer is worth finding before you start building.