Bringing clarity to complex engineering interface

Supporting SSEN’s engineering interface with National Grid on the Iver 132kV GIS programme.

At a glance

icon

Major upgrade

The Iver 132kV GIS programme is a major upgrade to the transmission infrastructure at National Grid Electricity Transmission’s (NGET) Iver substation.

Upgrading three super grid transformers

The programme involves upgrading three super grid transformers (SGTs) to facilitate a new 132kV gas-insulated switchgear (GIS) installation. The new installation will replace an ageing air-insulated switchgear (AIS) substation and help to satisfy increasing demand coming from London and Slough.

icon

Providing technical and compliance advice

Yova was appointed by SSEN as Engineering Consultant. We provided technical and compliance advice to support its interactions with NGET throughout the programme.

The challenge

Projects at the interface between a Distribution Network Operator and a Transmission Owner are never straightforward. Two organisations means two sets of governance structures, technical assurance requirements, and approval processes. And on Iver, the interface was made more challenging by the need for SSEN to deliver elements of NGET infrastructure itself.

Because of the technology constraints associated with GIS, SSEN needed to undertake ‘user self-build’ works for parts of the NGET-related scope. That meant SSEN demonstrating to NGET that its approach met NGET’s own technical, design and safety standard for assets that would ordinarily be designed, installed, tested and commissioned by the Transmission Owner.

Add the technical and safety complexity of upgrading SGTs and installing GIS within a live substation environment, and there was plenty to navigate.

The challenge meant both understanding these complex requirements, and meeting them in practice. Then, providing the evidence needed to demonstrate compliance.

We got to work.

Our approach

We started by supporting SSEN’s day-to-day engineering interactions with NGET during the early development of the programme.

We helped navigate the practical and technical touchpoints between the two organisations as the scope of the SGT and GIS works developed, providing a clear line of technical and process advice as requirements evolved.

As the programme moved into design, our role became more focused. We reviewed the relevant NGET policies and procedures, and advised SSEN on how to structure and evidence its approach.

The aim was straightforward: to help ensure the self-build route for the GIS-related works remained achievable while addressing NGET’s technical, design and safety expectations.

It was about getting into the detail, understanding what the requirements meant in practice, and helping SSEN build an approach that could stand up to scrutiny.

The outcome

We supported SSEN through the early development and design phases of the Iver programme, providing continuity of technical and process advice for almost two years.

During that time, the interface with NGET continued to evolve, as did the requirements surrounding self-build compliance. We provided the practical engineering insight needed to help SSEN navigate that change and maintain a clear route through the technical and compliance requirements.

Complex infrastructure depends on good interfaces. Yova helped make sure this one stayed connected.

hi-vis jacket Yova man on site

Related case studies

Yova Engineers on site hi-vis

Keeping complex projects connected

Keeping complex projects connected

Coordinating principal designer duties across a multi-site HV transmission programme.

Site survey yova - power grid

Making the right call before a route is set

Making the right call before a route is set

Creyke Beck to High Marnham.

Norwich Main substation extension

Powering the next phase of the energy transition

Powering the next phase of the energy transition

Norwich Main substation extension.

Stuck? You need Yova

Yova is your go-to partner when projects slow down. We’ll get you moving again.