I’m very excited to share that I’ve been appointed Principal Designer’s Representative (PD Rep) on one of the largest high-voltage transmission upgrade programmes currently underway in the UK. This is a multi-site scheme spanning several substations, and involving a complex web of specialist designers, contractors and third parties. Excited might be an understatement.
It’s also an appointment I don’t take lightly. Programmes of this scale don’t come around often, and being trusted to represent the Principal Designer’s function on it? One of the highlights of my career so far.
Why the PD Rep role matters so much
This PD Rep appointment is both specific and deliberate. So instead of taking on the full breadth of Principal Designer duties, it lets me focus where I can add the most value. And that would be in hazard identification and review, and the discipline of record-keeping that CDM 2015 rightly demands but that, on a programme this size, becomes a hefty engineering challenge in its own right. It’s a good thing I like a challenge.
This role also puts me at the centre of something I find intriguing, which is the flow of information. I’ll be between specialist designers working on different disciplines, and design teams working on different sites within the same programme. On a project of this scale, it’s as impactful to safety to keep that information moving in one clean, traceable flow as any one technical decision.
several substations, and involving a complex web of specialist designers, contractors and third parties. Excited might be an understatement.
It’s also an appointment I don’t take lightly. Programmes of this scale don’t come around often, and being trusted to represent the Principal Designer’s function on it? One of the highlights of my career so far.
Bringing consistency to scale
One of the things I’m most excited about is the chance to bring some consistency across a programme operating at this scale. When you’re coordinating hazard data, design risk and record-keeping across multiple sites and multiple design organisations, small inconsistencies can build up fast. My job will be to get the structure right early on, so that a hazard identified on one site is captured, communicated and closed out the same way everywhere.
I’m at the very start of this process. There’s still a lot to do, but I’m eager to get stuck in.
CDM wasn’t built with programmes like this in mind
If you want my opinion, CDM 2015, for all its strengths, wasn’t written with programmes of this scale and complexity in mind. The regulations do a great job of setting out what’s needed on a single project, but they don’t help to manage the sheer administrative weight of doing it consistently across lots of interlinked sites and design teams, all at once.
In my experience, that burden is more of a hurdle than the technical hazard identification itself, on a programme like this one. It’s the very reason we’ve been developing bespoke approaches to deal with it directly.
We made a tiered hazard register structured to reflect the layered nature of a programme like this (rather than a single flat register trying to do everything at once). We also created custom software tooling to take the manual weight out of tracking, chasing, and recording data across sites.
Neither of those is a shortcut around CDM’s requirements, of course. If anything, they’re an attempt to meet them properly at a scale the regulations don’t quite cater for.
It may be early days, but I’m thrilled about where this role will take me. It’s got me buzzing about what the wider industry could learn from our approach coordination on programmes like this one.